And We Have Dates!
In anticipation of the never-soon-enough C-Day in June (when actual construction starts), we now have critical dates for the Refresh Project.
Dining
First the Good News:
All dining spaces will be available until October/November 2025
Now the Critical Dates:
April 21, 2025 The Private Dining Room will be emptied
May 1, 2025 Building begins on for the Temporary Kitchen
The ATM machine has already been moved to the corridor by the Computer Room
The timeclock will be moved to the lobby area
Employees will use employee lockers on the terrace for coats and things
Fitness Center
April 21, 2025 Group fitness classes will take place in the Gathering Room until completion of Phase 1
May 1- 3, 2025 Fitness Center will be unavailable in order to accommodate the building of a temporary safety wall
A majority of the current equipment will be available throughout Phase 1 of the Refresh construction process
Pool
May 21, 2025 As of this date, the pool will not be available. The Administration is working through the final details of an alternate location.
Terrace
June 1, 2025 As of this date, the Terrace will not be available. The Administration will work to organize outside seating areas with shade.
Community Level Offices (C-Level)
July 2, 2025 As of this date, Resident Association Office, Human Resources, Resident Services, and Riverview Conference Room will not be available.
Human Resources — relocating to Mary Powell, Room 1214
Resident Services — relocating to Mary Powell, 1213
Conference Room — relocating to Mary Powell, 1314
Resident Association Office files have been scanned. Filing cabinets and copier will be moved to Mary Powell, 1213